Integrated Power Supply for Pellet Production Facility – Design and Construction of Electrical Infrastructure
About the project
Challenge
Location: Ukraine
Client: NDA
Status: Completed
Services Provided
Power Substations and Transmission Lines: Design, Construction, and Maintenance

Services provided
Voltage Group delivered a full scope of design and build services, including:
Development of project design documentation for power systems.
Construction of a 10 kV overhead power line from the grid to the facility.
Installation of two 10/0.4 kV transformer substations, each rated at 1600 kVA.
Busbar system installation rated for 2500 A.
Deployment of internal and external electrical networks throughout the facility.
Installation of lighting systems, lightning protection, and automation networks for production equipment.
Outcome
The facility was successfully connected to the power grid and provided with a stable, high-capacity energy supply, enabling the launch of modern pellet production operations. Voltage Group’s comprehensive engineering and construction approach resulted in full compliance with technical requirements, reduced energy risks, and accelerated commissioning of the plant.